·By Ablola, Saribong & Gueco Law Offices · researched and citation-checked against the firm's law library

Construction Delays and Liquidated Damages: Defining Substantial Completion in Philippine Law

Philippine Supreme Court clarifies when liquidated damages stop accruing in construction delays—actual substantial completion, not projections, matters.


The Supreme Court's 2017 ruling in Werr Corporation International v. Highlands Prime, Inc. (G.R. Nos. 187543 and 187580) clarifies a critical question in Philippine construction law: when do liquidated damages for delay stop accruing? The answer matters to both project owners and contractors because it determines how much a delayed contractor ultimately pays—and how much an owner can recover.

The case involved a dispute over the "The Horizon-Westridge Project" in Tagaytay. The owner, Highlands Prime, Inc. (HPI), hired contractor Werr Corporation International (Werr) to build 54 residential units under a General Building Agreement. The contract price was P271,797,900.00, with completion due within 210 calendar days. The contract included a liquidated damages clause: 1/10 of 1% of the contract price (P271,797.90) for every day of delay.

The project was not completed on time. HPI granted several extensions, with a final deadline of October 15, 2006. When Werr still failed to finish, HPI terminated the contract on November 28, 2006. Werr sought the balance of its retention money before the Construction Industry Arbitration Commission (CIAC), while HPI counterclaimed for liquidated damages for the delay.

The Dispute: How Long Do Liquidated Damages Run?

The central legal issue was the period for computing liquidated damages. Werr argued that industry practice, reflected in CIAP Document No. 102 (the "Uniform General Conditions of Contract for Private Construction"), provides that liquidated damages do not accrue after "substantial completion" of the project—defined as completing 95% of the work.

The CIAC agreed with Werr's theory but applied it creatively. Since Werr had achieved only 93.18% completion at its last billing, the CIAC projected when Werr would reach 95% based on its past performance rate. It computed 9.327 days of delay and awarded liquidated damages of about P2.5 million.

The Court of Appeals disagreed, computing delay from October 27, 2006 until termination on November 28, 2006—33 days—resulting in liquidated damages of P8,969,330.70. The CA reasoned that the contract's liquidated damages clause prevails over industry practice.

The Supreme Court's Ruling

The Supreme Court affirmed the CA's computation but rejected its reasoning. The Court held that industry practice does supplement private construction contracts, citing Articles 1234 and 1376 of the Civil Code. Article 1234 allows a contractor who substantially performed in good faith to recover as though there had been strict fulfillment, less damages. Article 1376 provides that usage or custom fills omissions in contract stipulations.

The Court noted that CIAP Document No. 102 was expressly intended to have suppletory effect on private construction contracts, as stated in CIAP Board Resolution No. 1-98.

However, the Court drew a crucial distinction: the effects of substantial completion apply only when the contractor actually achieves 95% completion. In prior cases like Diesel Construction Co., Inc. v. UPSI Property Holdings, Inc. and Transcept Construction and Management Professionals, Inc. v. Aguilar, contractors were excused from liquidated damages because they had proven completion rates of 97.56% and 98.16%, respectively.

Here, Werr failed to prove it reached 95% before termination. Its last admitted accomplishment was 93.18%, and it presented no evidence of work performed between the last billing and termination. The Court rejected the CIAC's approach of projecting when substantial completion would occur based on past billing rates. The Court explained that projecting substantial completion would create an iniquitous situation where the owner bears the risks and costs for the period excused from liquidated damages.

Other Rulings

The Court also affirmed the CIAC's factual findings on charges against the retention money. Under Executive Order No. 1008, CIAC arbitral awards are final and binding except on questions of law. The Court refused to review factual issues—such as whether payments to suppliers and contractors after termination were chargeable to retention—because these were properly resolved by the CIAC and affirmed by the CA.

Finally, the Court upheld the equal division of arbitration costs and denied attorney's fees, finding no bad faith on either side.

Practical Takeaways

  • Substantial completion is an actual, provable fact. A contractor cannot claim the benefit of the 95% substantial completion rule unless it can present evidence—such as progress billings or certificates—showing it actually achieved that rate.

  • Do not rely on projections. The CIAC's method of projecting a completion date based on past performance rates was rejected. Liquidated damages run until actual completion or termination, not until a hypothetical substantial completion date.

  • Industry practice supplements, not supplants, contracts. CIAP Document No. 102 and similar standards fill gaps in construction contracts. They do not override express stipulations, but they can clarify omissions—such as when liquidated damages stop accruing.

  • CIAC findings on facts are hard to overturn. Arbitral awards are final on factual matters. Parties should present complete evidence at arbitration, as appellate review is limited to questions of law.

  • Draft contracts with precision. Owners and contractors should specify in their agreements what constitutes substantial completion and when liquidated damages cease, to avoid costly disputes over these issues.

This article is general information and not legal advice. For your specific situation, consult a lawyer or ask ASG Legal AI.

This topic sits within our Litigation & Dispute Resolution practice.

Related reading

Have a question about this topic?

This article is general information, not legal advice. Ask ASG Legal AI for a cited, plain-language answer on your own situation — free, no sign-up.